101 Embankment, Manchester — two modern glass office towers at the Embankment development
✦ Dilapidations · Manchester

101 Embankment, Manchester

Large-scale interior dilapidation — full strip-out of partitions, kitchen, booth seating, AV infrastructure and mechanical & electrical installations

Location Manchester
Scope Office Dilapidations
Scale Large-scale Strip-out
Works Full Interior Strip-out
Status Completed
Project Overview

A full interior strip-out at one of Manchester's flagship offices

101 Embankment is part of a landmark commercial development in Manchester city centre. At the end of the tenancy, the outgoing occupier was required to return the space to landlord condition — a significant undertaking given the bespoke fit-out in place, which included a full kitchen canopy installation, feature booth seating and huts, a mezzanine-level AV suite, and extensive IT infrastructure.

Renova Projects UK was appointed to carry out the full dilapidation works in accordance with the schedule of dilapidations and contract drawings. Works were carried out across two distinct areas: the main floor, which housed the kitchen, café seating, vending and breakout facilities; and the lower presentation space, which contained UPS equipment, comms infrastructure, fan coil units and external condensers.

On completion, all surfaces were made good and the space handed back vacuumed and clean, ready for the landlord's incoming programme.

Scope of Works
  • 01
    Furniture, racking and loose fixtures strip-out All furniture, tenant signage, vending equipment and loose items removed from both floors
  • 02
    Kitchen and catering facility removal Full strip-out of kitchen canopy, catering equipment, worktops, base units, cold water feeds and drainage — all services capped and made safe
  • 03
    Booth seating and feature huts removal All bespoke booth seating, tables and timber feature huts dismantled and removed
  • 04
    AV, IT and cabling strip-out All AV equipment, Wi-Fi points, comms cabinets and associated cabling removed; feeds terminated at distribution boards
  • 05
    Partitions and doors removed to drawing Partitions and doors removed as indicated on contract drawings; all disturbed surfaces made good
  • 06
    Mechanical & electrical removal UPS, switchboards, fan coil units and external condensers de-gassed and removed; drainage capped; space cleaned throughout
Project Photography

On site at 101 Embankment

Planning a Dilapidation?

Have a dilapidation project
we can help with?

We handle end-of-lease dilapidations across the UK — from targeted make-good works to large-scale full strip-outs. Get in touch for a free, no-obligation consultation.

Related Services
← Back to
All Projects
→